Calendar of Events Competive Bidding Process Activities

 

Activity                                                                                                     

                              Date                                                            

MRO Application         

  Thursday, July 31, 2008

Electronic Data Room Activated

  Tuesday, October 14, 2008

Expected PUCO Decision on MRO

Wednesday, October 29, 2008

Announcement of minimum and maximum starting prices, number and size of tranches, load caps, Bid Participation Fee, Application Forms posted

Thursday, October 30, 2008

Information Session for Bidders

Thursday, November 6, 2008

Information Session for Bidders

Thursday, November 13, 2008

Deadline to submit Part 1 Application

Tuesday, December 2, 2008

Applicants are notified of Part 1 Application results no later than

Monday, December 8, 2008

Update to MW - measure of tranches, if necessary

Friday, November 28, 2008

Latest data for final decision on ESP

Wednesday, December 10, 2008

Deadline to submit Part 2 Application

 Friday, December 12, 2008

Applicants are notified of Part 2 Application results

Wednesday, December 17, 2008

Tranche Fee is announced

Monday, December 22, 2008

CBP Manager provided additional information on CBP parameters to bidders (decrements, excess supply, etc.)

Monday, December 22, 2008

Practical Training for Registered Bidders

Tuesday, December 23, 2008

CBP Manager informs Registered Bidders of starting prices

 Friday, December 26, 2008

Bidding Starts

Monday, December 29, 2008

CBP Manager submits a confidential report to the PUCO

Monday, December 29, 2008

Bids effective

Wednesday, December 31, 2008

Winning Suppliers SSO Agreements effective

Thursday, January 1, 2009

  (11/17/08)